Plot ratio, properly gross plot ratio (GPR), is a development's Gross Floor Area divided by its site area. URA fixes it for each site in the Master Plan. Multiply it by the site area and you get the most floor area the site can carry, before any bonus GFA. A GPR of 2.8 on a 10,000m² site means up to 28,000m² of GFA. URA is explicit that this is an upper bound that site conditions may stop you reaching.
The definitions below come from URA's development control handbook, its Master Plan 2025 gazette circular and its landed housing envelope guidelines, read on 25 November 2026. URA amends the Master Plan and its handbooks regularly, so let your Qualified Person confirm the figures for any site you are buying or designing.
The formula
Maximum GFA = Master Plan GPR × site area. Site area is measured between the survey boundary lines, which is why the land parcel's Certified Plan from SLA matters (see INLIS). URA's handbook adds one helpful rule: land set aside for drainage or road reserve that will be vested in the State may be included in the site area when computing GFA for the GPR. So the land you give up for a road widening does not automatically shrink what you can build.
The GFA side of the equation has its own rules: what counts, what is exempt, and the middle-of-wall measurement URA adopted in 2023. Those are in GFA. The two pages are halves of one calculation.
Reading the Master Plan
The current plan is Master Plan 2025, which URA gazetted on 1 December 2025 as the statutory land use plan for the next 10 to 15 years. Each site carries a land use zone, such as Residential or Commercial, and where the zone is density-controlled, a GPR figure. URA publishes the plan online, and the hard copy and the Written Statement are on view at The URA Centre.
The base plan is not the whole story. URA gazettes amendments to Master Plan 2025 through the year, some of which change a site's zoning or plot ratio, and lists them on its amendments page. Check both before relying on a figure, and check the date on any figure quoted to you by an agent or a listing.
Why it is a ceiling
URA's words: "The MP plot ratio is the upper bound" and it "may not always be achievable". The reasons URA gives are the ones that decide most feasibility studies:
- the shape of the plot, site topography or ground conditions;
- building setbacks;
- building height controls; and
- the technical requirements of other authorities.
So the GPR tells you the most you could ask for. Whether the site will actually take it is a design question for an architect, worked out against setbacks, height and the other agencies' rules.
Bonus GFA
Some floor area can sit above the Master Plan GPR through URA's incentive schemes. URA keeps the cumulative bonus within an overall budget of 10% above the Master Plan GPR, or the maximum allowable GFA of the development, and each scheme has its own sub-cap: 7% of proposed residential GFA for balconies, private enclosed spaces and private roof terraces, 1% for indoor recreation spaces. Bonus GFA already used cannot be carried over when the site is redeveloped. The detail sits in GFA.
Landed housing
Landed homes are controlled differently. Since 11 May 2015, URA's envelope control guidelines define the allowable building envelope for landed housing by storey height and setbacks. Landed housing may not exceed the 2-storey or 3-storey height control, or the storey height shown in the designated landed housing plan in the Master Plan, whichever is lower. The maximum building height is 12m in a 2-storey area and 15.5m in a 3-storey area. For a house, then, the questions are storeys, height and setbacks, not a GPR multiplication.
Existing buildings
For a building that already stands, the useful question is how much of the permitted GFA is already used. That needs the existing GFA, and the existing GFA needs drawings that match the building. In older buildings they often do not: enclosed balconies, infilled voids and mezzanines added over the years all count, and none of them may be on the approved plans. URA's GFA Verification e-service lets a Qualified Person check a building's GFA with URA, but it needs a CAD or BIM calculation plan to start from.